Site Layout Note that the layout of the construction site may change from year to year. The following instructions are intended to be general enough to handle the various configurations that have been and will be used over the years. Some elements such as skew, floodways, environmentally sensitive areas, rivers, etc. may not appear in some years.
The
competition construction site should be accessible for delivery of materials and
should be relatively level. Paved
areas, such as floors and parking lots, work well.
A smooth and level ground surface is needed at the location where bridges
are constructed and dimensions are checked since clearances are measured from
the ground. Load testing requires
rigid (i.e. Portland cement concrete if possible) pavement that is level and smooth.
If rigid pavement is not accessible, provision must be made to prevent
bridges from sinking into the supporting surface during load testing.
Depending
on the schedule and the number of competitors, it may be necessary to provide
several construction areas and/or several load testing areas so that several
bridges may compete simultaneously. Depending on the deflection measurement
methods, the load testing area tends to be the slowest station in the sequence
so it is advisable to have more load stations than construction areas if there
are more than five or six bridges in the competition.
Spectators
should have visual access to the competition.
However, the bridge construction and load testing areas should be
cordoned to keep spectators at a safe distance and to prevent interference with
competitors and judges.
The
river, floodway, environmentally sensitive areas, islands, docks, footings, site boundaries, staging yards
and other site features as specified in the current rules may be marked with chalk,
paint, tape, ribbon or any other material that is durable enough to last through
the competition. See Figure 1 for an example of a well laid out site. Figure #1: Typical Site Layout
River
and parkway boundaries should be accurately spaced and parallel, and the skew,
footings, docks, moorages and other features that may be required by the current
rules should be
carefully measured and placed. 2009 Taping Plan Drawings: 2009NSSBC_TapingPlan.dwg, 2009NSSBC_TapingPlan.dxf
LAYING OUT
THE SITE TAKES LOTS OF TIME. You should
plan to have the site ready well before the beginning of the competition. Space will be needed to display and store completed bridges while they wait for their turn in the loading station. It is a good idea to draw the overall site plan (erection area, load area, weighing area, storage area, spectator access, etc...) to scale when choosing a site to ensure that there is adequate room for all parts of the competition. The attached taping plan drawing can be imported into a CAD file to ensure that adequate space is available. Outdoor sites should plan on having access to lighting in case the competition goes longer than expected and the loading must continue in the dark. |